What are resource costs?

Resource costs are determined by using the hourly rate of the resource and the billing rate. Resource hourly rates are set by the Organization application and Schedule Manager.

Using the Cost dialog box, you create, modify, and display cost information regarding resource costs. It also allows you to define fixed costs associated with both schedules and tasks.