Update program deliverable dependencies sequence

As you create, modify, or remove deliverable dependencies, Active Workspace prompts you to resequence the program deliverables. If you select No from this prompt, you can manually resequence the deliverables from the event's Deliverables tab at a later time.

Procedure

  1. Navigate to the event's Deliverables tab in your program, project, or subproject.
  2. Click Update deliverable sequence. A prompt appears asking you to resequence the deliverables:
    • Yes — Starts the resequencing process. The amount of time this takes depends on the number of deliverable dependencies created, modified, and removed.
    • Run in Background — Runs the resequencing process in the background so you can continue working. Select this option if you created, modified, or removed a large number of deliverable dependencies.
    • No — Closes the prompt without taking any action. You can click Update deliverable sequence again later to view the prompt and resequence your deliverables.

Once resequencing is complete, Active Workspace adjusts the deliverable sequence and updates the Sequence column if necessary.