Schedule Management on Active Workspace > Updating your schedule tasks > Update the status of a schedule task
Update the status of a schedule task
As a team member, as you complete work on a schedule task, you can manually update the Execution Properties values to show the schedule task's current status. If you are updating a schedule task that is associated with a workflow, these status values may be automatically updated as the workflow progresses, but you can still manually modify the values, if appropriate.
You can update properties on a single schedule task, multiple schedule tasks, or on the schedule task's Information panel.
Update properties on a single schedule task
- Select the desired schedule from the folder structure or from the Gantt view.
- Click Edit.
- Edit the schedule task's properties.
- Click Save.
Update properties on multiple schedule tasks
This display method enables you to update properties directly within the table. It's a convenient method to use to update properties on more than one schedule task.
- Select the Table display method.
- Click Edit.
- Edit the schedule tasks' properties in the table.
- Click Save Edits.
Update schedule task properties in the Information panel
You can access the Information panel from within any display method.
- Select the desired schedule task.
- Click Information.
- Select the Execution Properties tab.
- Click Edit.
- Edit the schedule task's properties.
- Click Save.