Schedule Management on Active Workspace > Updating your schedule tasks > Update the status of a schedule task

Update the status of a schedule task

As a team member, as you complete work on a schedule task, you can manually update the Execution Properties values to show the schedule task's current status. If you are updating a schedule task that is associated with a workflow, these status values may be automatically updated as the workflow progresses, but you can still manually modify the values, if appropriate.

You can update properties on a single schedule task, multiple schedule tasks, or on the schedule task's Information panel.

Update properties on a single schedule task

  1. Select the desired schedule from the folder structure or from the Gantt view.
  2. Click Edit.
  3. Edit the schedule task's properties.
  4. Click Save.

Update properties on multiple schedule tasks

This display method enables you to update properties directly within the table. It's a convenient method to use to update properties on more than one schedule task.

  1. Select the Table display method.
  2. Click Edit.
  3. Edit the schedule tasks' properties in the table.
  4. Click Save Edits.

Update schedule task properties in the Information panel

You can access the Information panel from within any display method.

  1. Select the desired schedule task.
  2. Click Information.
  3. Select the Execution Properties tab.
  4. Click Edit.
  5. Edit the schedule task's properties.
  6. Click Save.