Drag a proxy task

You can place the proxy task anywhere in the structure by simply dragging it up or down in the tree table.

Proxy tasks are shown in the hierarchy based on a reference task — the task which was selected when first creating the proxy. In the case of cross-schedule dependencies, the proxy typically references the task on which it depends.

The proxy is placed above or below its reference task based on the start date:

  • If the proxy starts before or at the same time as its reference task, it displays above the reference task.
  • If the proxy starts after the reference task, it displays below the reference task.

Results

Note: Data in a proxy task does not roll up to any summary task.