As work proceeds on a project, the project manager can manually update the project or subproject properties to reflect the current project state. You can update properties on a single project, multiple projects, or on the Information panel.

Update properties on a single project or subproject

You can update properties on a single project in the folder structure or from the program timeline.

Procedure

  1. Select the desired project from the list.
  2. Click Edit.
  3. Edit the project's properties.
  4. Click Save.

Update properties on multiple projects or subprojects

This display method enables you to update properties directly within the table. It's a convenient method to use to update properties on more than one project or subproject.

Note: You can also update properties on multiple projects or subprojects from the program timeline.

Procedure

  1. Select the Table display method.
  2. Using multiselect mode, select the projects from the list.
  3. Click Edit.
  4. Edit project or subproject properties in the table.
  5. Click Save Edits.

Update project or subproject properties in the Information panel

You can access the Information panel from within any display method.

Procedure

  1. Select the desired project or subproject.
  2. Click Information.
  3. Click Edit.
  4. Edit the project or subproject properties.
  5. Click Save.