TeamcenterKnowledge

Schedule Management > Creating and managing schedules > Structuring subschedules > Managing master schedules

Creating a master schedule

A master schedule contains one or more subschedules. You can add schedules and remove subschedules from the master schedule.

Before you create a master schedule, verify:

  • All candidate subschedules have their Published attribute set to True. Schedules that have their Published attribute set to False cannot be included in a master schedule.
  • The start and finish dates for all candidate subschedules must fall within the start and finish dates of the master schedule.

Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.plm00054/create_manage_master_schedule · retrieved 2026-07-10