Create a schedule baseline
As a schedule coordinator, you can create a baseline from the current schedule to use as a snapshot against which to compare the schedule at a future date.
In some cases, it may take Active Workspace time to create the schedule baseline. You can check your Alerts to see if the process has completed.
Procedure
Navigate to the desired schedule and open it.
From the Gantt chart view, click More Commands > New > Create Baseline.
On the Baseline Schedule panel:
In the Name box, enter a meaningful name for this baseline, if desired. The default value is the schedule name.
In the Description box, enter a meaningful description for this baseline, if desired.
Select Active to make this baseline the active baseline. The active baseline information is shown for the baseline columns when not viewing a specific baseline.
Note: If this is the first baseline for this schedule, this option does not display — Teamcenter automatically sets this baseline as active.
Click Create.