Schedule Management > Allocating requirements to Schedule Manager tasks > Generate a traceability report
Generate a traceability report
The traceability report shows information about defining and complying objects related to the trace link.
Using the traceability report, you can also manage trace links, including: delete a trace link, view trace link properties, and navigate to the trace-linked object.
Procedure
- Select a task in Schedule Manager on which a trace link exists.
- Choose Tools→Trace Link→Traceability Report, and then choose either Defining or Complying.
Results
Tip: The signoff status on target requirements is indicated by:
- A workflow completed symbol next to the target requirement in the schedule task structure.
- Information in the workflow logs shown on the Audit Logs tab in the Summary view.
Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.plm00054/generating_traceability_report · retrieved 2026-07-10