Schedule Management > Allocating requirements to Schedule Manager tasks > Generate a traceability report

Generate a traceability report

The traceability report shows information about defining and complying objects related to the trace link.

Using the traceability report, you can also manage trace links, including: delete a trace link, view trace link properties, and navigate to the trace-linked object.

Procedure

  1. Select a task in Schedule Manager on which a trace link exists.
  2. Choose Tools→Trace Link→Traceability Report, and then choose either Defining or Complying.

Results

Tip: The signoff status on target requirements is indicated by:

  • A workflow completed symbol next to the target requirement in the schedule task structure.
  • Information in the workflow logs shown on the Audit Logs tab in the Summary view.