Schedule Management > Creating and managing schedules > Phase gate schedules and tasks
Create a phase gate schedule
Procedure
Create a schedule by following the procedures in Create a schedule using the New Schedule wizard.
Choose File→New→Task.
Schedule Manager displays the New Task dialog box.
Update task properties in the New Task dialog box by following the procedures in Add a task using the New Task wizard. Be sure to check the Create Phase Gate Schedule box.
After you complete the task, the schedule displays a phase, two milestones, and a gate. The phase appears as hatched lines.
Repeat this process to add additional phases.