Manage schedule baselines

Procedure

  1. Select the schedule and choose Schedule→Manage baselines.

    Teamcenter displays the Manage Baselines dialog box.

  2. To make a baseline the active baseline: select a baseline from the list and click Set Active.

  3. To add a new schedule baseline, click Add Baseline.

  4. To modify a baseline name: select a baseline from the list and, under the Baseline name column, enter a new name.

  5. To delete a baseline: select a baseline from the list, click Delete Baseline, and in the Confirmation dialog box click Yes.

  6. Click Close.