Schedule Management > Creating and managing schedules > Determining resource availability with resource graphs
View a resource graph from Organization
Procedure
In the lower-left pane of the Organization application, right-click Users and choose View Resource Graph.
Note: You must either be a member of the Resource Graph Viewers role, or a member of a custom role that has been added to the
SM_RESOURCE_GRAPH_VIEWER_ROLEpreference, to open resource graphs; otherwise, the Show Resource Graph command is disabled.Double-click Users to expand the list and click a user.
The resource graph displays a stacked bar chart with that user's daily task workload.
The default resource graph starts one week prior to the schedule start date and spans 15 weeks (ending one week prior to the schedule end date).
To view another user's resource graph, click that user. Enabling a resource graph for one user displays resource graphs for all users.
To hide the resource graph, right-click Users and choose View Resource Graph again.