TeamcenterKnowledge

Schedule Management > Creating and managing schedules > Defining tasks, milestones, and work breakdowns > Creating dependencies between tasks

Add a proxy task

Procedure

  1. Open an original schedule you've created within the Schedule Manager application.

  2. Choose File → New → Proxy Task.

    Teamcenter displays the Select a Schedule page in the New Proxy Task wizard.

  3. Select the schedule on which to depend.

  4. Click Next.

    Teamcenter displays the Select a Task page.

  5. Select the task on which to depend.

  6. Click Finish.

The proxy task appears grayed out in the schedule.