Viewing and updating your task information
You can see the tasks you are assigned across all schedules in the Schedule Tasks folder in My Worklist in the rich client.
From the My Tasks tab, you can:
- Mark tasks as complete.
- Display the State column, which groups status.
- Edit and update execution column data, such as the actual finish date, actual start date, work complete percent, task status, and work complete.
- Reorder column headers by clicking and dragging the header to the desired position.
- Sort the task list by clicking the column header of the column you want to sort.
- Limit the number of tasks displayed per window.
- Filter the tasks by a specific duration such as week, month, or year.
- Update the task execution information by adding values in the appropriate fields, and then clicking Update Tasks.
- Save any changes to the column configuration settings, like the number of tasks shown on a page by clicking Save Configuration.