Set options for the earned value management calculation

Procedure

  1. In the Schedule Manager application, select the root node in the tree.

  2. Choose View→EVM→EVM Options.

    The Earned Value Calculation dialog box is displayed.

  3. Select Cost or Hours for the basis of the calculation.

  4. Choose one of the following from the Calculate Work Complete By list:

    • Percent Complete
    • Actual Hours
  5. Select one of the following labels:

    • Earned value based management based labels
    • Cost/Schedule control systems criteria

    Select Help Me Choose for label definitions.

  6. Click Calculate.

    The EVM Results dialog box is displayed.