Program Planning > Defining the plan > Creating, managing, and assigning projects and subprojects > Add a subproject to a project
Add a subproject to a project
As the program manager, you can add one or more subprojects to a project.
Procedure
- Select a program and click Open.
- Select a project from the timeline list and click More Commands > New > Add Plan Level.
- In the Add Plan Level panel, specify the Type and enter the subproject properties.
- Click Add.
The subproject appears beneath the master project in the timeline.