Add a subproject to a project

As the program manager, you can add one or more subprojects to a project.

Procedure

  1. Select a program and click Open.
  2. Select a project from the timeline list and click More Commands > New > Add Plan Level.
  3. In the Add Plan Level panel, specify the Type and enter the subproject properties.
  4. Click Add.

The subproject appears beneath the master project in the timeline.