Generate a program schedule

After the network diagram is finalized, create the schedule for the program by assigning it a start date. Add or adjust the span time for each WBS work package, as necessary. Before the schedule can be generated, you may have to adjust the available resource for each labor category in the external schedule.

Once the schedule is generated, the system assigns each WBS work package (represented by a schedule task in the schedule) an early start and an early end date along with any slack available to execute that task.

The schedule data for each work package is then sent to Teamcenter and is populated as Task Info. This information is visible when executing this task in the Active Workspace.