Schedule Management > Creating and managing schedules > Defining tasks, milestones, and work breakdowns > Creating dependencies between tasks
Create task dependencies (task table)
Procedure
Select a task in the task table.
Define the task dependency information:
- If the selected task is dependent on another task, double-click the Predecessor cell.
- If another task is dependent on the selected task, double-click the Successor cell.
Enter a task number, type of dependency, and lag time in the following format:
task-number[type][+/- lag]- type — one of the lag types:
SS(Start-to-start),FS(Finish-to-start, default),SF(Start-to-finish),FF(Finish-to-finish). - +/– — whether the lag time occurs after (
+) or before (-) the lag type. - lag — the lag time, specified in weeks (
w), days (d), or hours (h) suffix, or decimal values. Default unit is days (d), default value 0. Schedule Manager always converts and displays the lag time in days regardless of the suffix entered.
- type — one of the lag types:
Lag time examples (task number 1, lag type FS)
Assumes 1 work week = 5 days and 1 work day = 8 hours. Calculations are not valid if your working time per day is more than 8 hours.
| To set the lag time to | Enter | Schedule Manager displays |
|---|---|---|
| 2 weeks | 1FS+2w |
1FS+10d |
| 1 and one-half weeks | 1FS+1.5w |
1FS+7d4h |
| 4 days | 1FS+4d or 1FS+4 |
1FS+4d |
| 3 days and 4 hours | 1FS+3d4h or 1FS+3.5d |
1FS+3d4h |
| 10 hours | 1FS+10 or 1FS+1.25d |
1FS+1d2h |
| 6 hours and 30 minutes | 1FS+6.5h |
1FS+0d6.5h |
You can also create more than one dependency by using commas (for example, 5, 6SS-1, 7FS+4).
If you reorder tasks, the Predecessor and Successor boxes are automatically updated with new task numbers.
Note: Proxy tasks mirror real tasks. If you change the dependencies on the real task, the dependencies on the proxy task change as well.
Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.plm00054/create_task_dependencies_task_table · retrieved 2026-07-10