Add a project to a program

As the program manager, you can add one or more projects to a program. A project is an investment-oriented decomposition of the program to which it is assigned and may have an end-product orientation.

Procedure

  1. Select a program and click Open.
  2. Select the program on the timeline table (or do not select anything from the timeline table).

Note: If you select an existing project on the timeline list and add a plan level, you add a subproject to the selected project.

  1. Click More Commands > New > Add Plan Level.
  2. In the Add Plan Level panel, specify the Type and enter the project properties.

Tip: If you want to add multiple projects with the same or similar values, click Pin Panel to keep the Add Plan Level panel open as you create the projects.

  1. Click Add.

The new project appears on the timeline.