Schedule Management > Creating and managing schedules > Updating schedules
Recalculate a schedule's tasks and their dependencies
You can recalculate a schedule's tasks and their dependencies using the Recalculate Schedule option.
Procedure
Open the schedule in Schedule Manager and select any task or the schedule summary task.
Choose Schedule → Recalculate Schedule.
Teamcenter displays the Recalculate Schedule dialog box.
In the confirmation dialog box, click Yes.