Program Planning > Creating, managing, and assigning deliverables > Creating and managing program deliverable dependencies > View program deliverable sequence
View program deliverable sequence
You can view the program deliverable sequence in order to better plan how to work on the program deliverables.
Procedure
- Open the desired event from a program's timeline or from its Events tab.
- Click the event's Deliverables tab.
- The Sequence column in the list of deliverables displays the order in which the deliverables should be worked.
Active Workspace sets the deliverable sequence based on the dependencies created for the deliverables.