Schedule Management > Creating and managing schedules > Analyzing costs
Schedule cost information
Procedure
To display cost information for the schedule and, optionally, change the billing codes, select the schedule in the task tree, and choose Schedule → Costs.
Note: You can also set values for fixed costs for the schedule.
Schedule Manager displays the Costs dialog box for the selected schedule.
Example (Normal Schedule)
| Parameter (task-A) | Value |
|---|---|
| Resource hourly rate (User A) | $100.00 |
| Total duration of task | 16 hours |
| Time accrued | 8 hours |
| Parameter (task-R) | Value |
|---|---|
| Resource hourly rate (User B) | $125.00 |
| Total duration of task | 8 hours |
| Time accrued | 0 hours |
| Parameter (task-W) | Value |
|---|---|
| Resource hourly rate (User A and User B) | $100.00 for User A, $125.00 for User B |
| Total duration of task | 8 hours (4 hours each for User A and User B) |
| Time accrued | 0 hours |
The default values for Bill Code, Bill Sub-code, and Bill Type are unassigned. You can change these values using the Fixed Costs dialog box.
- Click Finish.