Display Schedule Manager information in My Teamcenter

You can display Schedule Manager information in My Teamcenter by creating and editing various default child properties and pseudofolder preferences. The following steps are an example; you can configure the preferences to suit your needs.

Procedure

  1. Set the Schedule_DefaultChildProperties preference to the following values:
    • IMAN_reference
    • project_list
    • schedule_deliverable_list
    • schedule_deliverable_taglist
    • fnd0SummaryTask
    • fnd0Schedulemember_taglist
  2. Set the ScheduleTask_DefaultChildProperties preference to the following values:
    • IMAN_reference
    • child_task_taglist
    • project_list
    • sch_task_deliverable_list
  3. Create the SchDeliverable_DefaultChildProperties preference as a user preference and set it to the following value:
    • deliverable_inst
  4. Create the Schedule_PseudoFolder preference as a user preference and set it to the following values:
    • schedule_deliverable_list
    • project_list
    • schedule_deliverable_taglist
    • fnd0Schedulemember_taglist
  5. Create the ScheduleTask_PseudoFolder preference as a site preference and set it to the following values:
    • sch_task_deliverable_list
    • task_deliverable_taglist

Results

If you configure your preferences as described, the Home folder displays the schedule and task deliverable/child information accordingly.