TeamcenterKnowledge

Schedule Management > Getting started with Schedule Manager > Schedule Manager menus

View menu

Command Description
Refresh (F5) Updates the information displayed for a selected line and all of its children.
View Properties (Alt+P) Shows the properties for the selected object.
View Baseline Displays the current baseline for the selected task or schedule.
Expand All Expands the complete substructure below the selected lines.
Collapse All Collapses the complete substructure below the selected lines.
EVM→EVM Options Sets the calculation basis for earned value management, either cost or hours, and whether to calculate the work complete by percent or actual hours. Also specifies the labels to be used in the results display.
EVM→EVM Calculations Calculates the earned value management values and displays them in the EVM Results dialog box.
Critical Path→View Critical Path Highlights the critical path in red in both the tree table and the Gantt chart or removes the highlight.
Critical Path→Set Color Sets the color for the critical path.
Zoom Factor→Week Displays the Gantt chart in a weekly format.
Zoom Factor→Month Displays the Gantt chart in a monthly format.
Zoom Factor→Quarter Displays the Gantt chart in a quarterly format.
Zoom Factor→Year Displays the Gantt chart in a yearly format.

Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.plm00054/xid646431 · retrieved 2026-07-10