As a functional organization user or leader, you can enter the progress of a functional work package any time during its execution. You enter progress as a percentage complete value using a scale of 1-100. The system calculates progress for a WBS work package by rolling up the percentage completion values of all its constituent work packages. As an IPT lead or program manager, you can review the percentage complete status of the WBS work package. You can then extract the progress information to create an EVMS status report in a format that can be exported to the EVMS software.

Procedure

  1. Open the FWP and click the Overview tab.
  2. Choose Edit → Start Edit and then update the Percentage Complete field in the Additional Properties section.