Set a task baseline

You can set baselines for schedules and tasks. When you create a baseline for a task, you add it to an existing schedule baseline.

Note: You must create a baseline for the entire schedule before you can baseline a single task. Baselines do not include proxy tasks or cross schedule dependencies.

Procedure

  1. Select the task or tasks.
  2. Choose Schedule→Baseline Task.
  3. From Choose baseline, select a schedule baseline under which the task baselines are to be added or updated.