You define details of the required work at the lowest level of the WBS work package. These work packages eventually map to a schedule task in the program schedule. The sequencing of these tasks is defined by creating predecessor relationships between the corresponding work packages. The outputs from the predecessor work packages become an input to that work package. The last work package in a predecessor-successor chain is linked to a criteria.

Assign a work package to its criteria as follows:

Procedure

  1. Select the WBS root and click the IMP tab.

  2. In the Event table, select the appropriate event.

    The Accomplishment table is populated.

  3. In the Accomplishment table, select the appropriate accomplishment.

    The Criteria table is populated.

  4. In the Criteria table, select the criteria to which the work package is to be assigned.

  5. From the work area toolbar of the Work Package section, click Add to.

  6. Use the Add panel to select the appropriate work package and click Add.

    The system assigns the work package to its criteria.