Add schedules to the master schedule

Procedure

  1. Open a schedule in Schedule Manager. This schedule becomes the master schedule. (You can also open an existing master schedule and add schedules to it.)

  2. Choose Schedule→Insert Schedule.

    Schedule Manager displays the Insert Schedules dialog box.

    Note: All candidate subschedules must have the Published attribute set to True to appear in the Insert Schedules dialog box. Schedules with this attribute set to False cannot be inserted into a master schedule.

  3. Choose one or more schedules from the Available Schedules section and click > to insert the schedules into the Selected Schedules section. To select all available schedules, click >>.

    Note: Baseline schedules cannot be inserted into a master schedule. Therefore, no baseline schedules are displayed in the Insert Schedules dialog box.

  4. Click OK.

Schedule Manager inserts the schedules into the master schedule and they are sequenced in the order of their start dates.