As the program manager, you can create a new project from an existing project within a program.
Note: When creating a project from a project template, you have the option of including the template's deliverables and checklists in the new project.
Procedure
- Select a program and click Open.
- Select a project from the timeline list and click More Commands > New > Save As.
- In the Save As panel, enter the project properties.
- (Optional) To create the new project in a different program, select the desired program in Target Plan Level.
Note: If your administrator has configured Teamcenter project security, the new project will be assigned to the same Teamcenter Tc_project as the parent program.
- (Optional) To include the program's checklists (including checklist questions) in this new project, select Include Checklists.
- (Optional) To include the program's deliverables (including deliverable instances and attachments) in this new project, select Include Deliverables.
- Click Save.