TeamcenterKnowledge

Schedule Management > Creating and managing schedules > Updating schedules

Update item display

You can ensure that a displayed schedule contains the most up-to-date list of assignments by refreshing or reloading the display using Refresh and Reload Schedule on the main toolbar.

You must first select the scheduled summary task to refresh that schedule.

The Refresh and Reload Schedule options are only available when the user is not in a Schedule Manager Deferred Session.

  • Refresh updates the schedule by adding all changes made to other parts of the schedule.
  • Reload Schedule reloads the entire list of assignments. This command recalculates the entire schedule before reloading when:
    • The schedule was exported from Microsoft Project using the TCUA-MSP plug-in.
    • The schedule is a master schedule in which one or more subschedule tasks was updated independent of the master (for example, if a user made changes to the subschedule).

Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.plm00054/xid1011977 · retrieved 2026-07-10