Identify predecessors for work packages
Link the work package as a predecessor of another work package as follows:
Procedure
In the WBS hierarchy, select the predecessor work package, and click Copy.
The system copies the work package to the clipboard.
Select the successor work package, click the Network tab, and click Paste from the work area toolbar of the WBS Predecessors section.
The system creates a link between the work packages.