Shift a schedule

When the projected timeline of a project changes, you can use the shift schedule feature to change the start and finish date of a schedule.

Note: Shifting a schedule on a master schedule shifts the subschedules. This action cannot be undone.

Procedure

  1. Select a schedule in Schedule Manager and choose Schedule → Shift Schedule.

    Teamcenter displays the Shift Schedule dialog box.

  2. Click the calendar button and either select a new schedule start date from the calendar and click OK, or double-click the new date.

  3. Click OK again.