When you are planning your program, you can drag your events to a new date on the program timeline. When you do this, you are asked if you want to automatically move any secondary events by the same number of days as the primary event. This is helpful if you have a large number of events that have dependent secondary events in your plan. You can also adjust the planned date from the Information Panel or by clicking Shift Event in the primary toolbar.
Shift an event's planned date on the program timeline
Procedure
- Select an event from the program timeline and drag it to the new date. If there are any dependent secondary events, you are asked if you want to move the secondary events to a future date.
- Do one of the following:
- Click Move to move all secondary events by the same number of days as the primary event. (Note: Only events for which you have write access will be moved.)
- Click Cancel to keep all secondary events at their current date.
Shift an event's planned date from the Information panel
Procedure
- Select the desired event from the program timeline and then click Information from the primary toolbar. The Information panel opens.
- Click Edit.
- Change the Planned date.
- Click the Keep Related Objects in sync with Planned Date check box to move the primary event's related artifacts, such as event criteria, checklists, and deliverables, by the same number of days to keep everything in sync.
- Click Save and then close the Information panel.
Shift an event's planned date from the primary toolbar
Procedure
- Select the desired event from the program timeline.
- Click More Commands > Edit > Shift Event. The Shift Event panel opens.
- Enter the new Planned Date.
- Click the Shift the secondary events check box to shift the secondary events by the same number of days as the selected event.
- Click Shift to change the event's planned date.