Create a dependency between a schedule milestone and a program event

You can create dependencies between a schedule milestone and a program, project, or subproject event on the program timeline.

Note: You can only create dependencies from past objects to future objects.

Procedure

  1. Open a program that has a schedule associated with it.
  2. Click Schedule Milestones and select Show All.
  3. Click Dependency.
  4. Hover over the target milestone or event. The connection points appear on either side of the target milestone or event.
  5. Click and drag the secondary object's connector, and then release it on the primary object's connector.