TeamcenterKnowledge

Schedule Management > Configuring Schedule Manager > Setting up work calendars

Update your calendar

When you create a schedule calendar, it inherits its data from the base calendar. When you change the schedule calendar or the base calendar, you must reset the calendar for changes to be seen in the other calendar.

Procedure

  1. Open the schedule calendar in Schedule Manager by choosing Schedule→Schedule Calendar. The schedule must be unpublished to work with the schedule calendar. To unpublish the schedule, change the Published schedule property to false.
  2. After you make your changes to the schedule calendar, click the Reset Calendar button. The Reset Schedule Calendar dialog box appears.
  3. To make all changes in the schedule calendar and base calendar appear in both, click the Merge with Base Calendar button and click OK.

Warning: If you leave the Reset to Base Calendar button selected and click OK, any changes you made to the schedule calendar are lost, and the base calendar replaces the schedule calendar.

Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.plm00054/xid646271 · retrieved 2026-07-10