Schedule Management > Creating and managing schedules > Defining tasks, milestones, and work breakdowns > Scheduling and managing tasks > Adding tasks to a schedule
Add a task using the Task box
Procedure
Open a schedule in Schedule Manager.
Select an existing task. The new task is inserted directly below (at the same level of) the currently selected task.
Enter the task name in the Task box at the top of the task table.
Note: You cannot restrict the task name length to 32 characters with the
TC_Allow_Longer_ID_Namepreference.In the Work box, enter the task work. You can specify the task work in weeks, days, or hours by adding the
w,d, orhsuffix to the value. You can also enter decimal values for task work, e.g.12.5h.The default task work is displayed in
h(hours) and the default value is 8. Regardless of the suffix specified, Schedule Manager converts and displays the task work in hours.Click Create.
The task defaults as starting on the current day and lasting for the same duration as the specified task work. For example, 40h entered in step 4 is used for both 40h work and a 40h duration.
Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.plm00054/using_task_box · retrieved 2026-07-10