TeamcenterKnowledge

Schedule Management > Exchanging data between Microsoft Project and Schedule Manager > Transferring special items

Transferring special items

Although many items in Microsoft Project transfer seamlessly to a schedule, some do not. This topic describes those special items that do not transfer directly.

Priorities

Microsoft Project supports a number-based priority system, while Schedule Manager supports level-based priorities.

Mapping on Export (Microsoft Project priority → Schedule Manager priority):

MS Project priority Schedule Manager priority
0–141 Lowest
142–283 Low
284–425 Medium low
426–567 Medium
568–709 High
710–851 Very high
852–1000 Highest

Mapping on Import (Schedule Manager priority → Microsoft Project priority):

Schedule Manager priority MS Project priority
Highest 1000
Very high 800
High 650
Medium 500
Medium low 400
Low 250
Lowest 100

Task state / percent complete

Microsoft Project does not support Schedule Manager's state types directly; states are derived from Percent Complete:

MS Project Percent Complete Schedule Manager state
100 COMPLETE
0 NOT STARTED
> 0 and < 100 IN PROGRESS

Note: The default status of the equivalent state is automatically set.

Other items that do not transfer or behave differently

  • Calendars cannot be imported or exported.

  • Split tasks are not supported by Schedule Manager. This option exists in the Microsoft Project plug-in but not in Schedule Manager. Workaround: in Microsoft Project, select Options from the Tools menu and clear the Split in-progress tasks option.

  • Constraints — Schedule Manager does not support all Microsoft Project constraints, and vice versa:

    Microsoft Project Schedule Manager
    ASAP ASAP
    ALAP ALAP
    Must start on Fixed
    Must finish on Fixed
    Start no earlier than None
    Start no later than None
    Finish no earlier than None
    Finish no later than None
  • Microsoft Project does not have the option of unlinking a task's Percent Complete from Work Complete. Workaround: before importing or exporting, make sure to check the Is Percent Linked option in Schedule Manager (open the Properties dialog box for a schedule; from the General tab, click Is Percent Linked).

  • The Microsoft Project plug-in does not support integrated projects (multiple Microsoft Project projects in the same project).

  • Baselines do not transfer for import/export operations.

  • When you import from Teamcenter to Microsoft Project, phase gates and proxy tasks are treated as normal tasks without any special attributes — only basic scheduling data is imported. No relationships with other Teamcenter objects are imported, including trace links, deliverables, and workflow information.

Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.plm00054/mpntegration3 · retrieved 2026-07-10