Schedule Management > Exchanging data between Microsoft Project and Schedule Manager > Transferring special items
Transferring special items
Although many items in Microsoft Project transfer seamlessly to a schedule, some do not. This topic describes those special items that do not transfer directly.
Priorities
Microsoft Project supports a number-based priority system, while Schedule Manager supports level-based priorities.
Mapping on Export (Microsoft Project priority → Schedule Manager priority):
| MS Project priority | Schedule Manager priority |
|---|---|
| 0–141 | Lowest |
| 142–283 | Low |
| 284–425 | Medium low |
| 426–567 | Medium |
| 568–709 | High |
| 710–851 | Very high |
| 852–1000 | Highest |
Mapping on Import (Schedule Manager priority → Microsoft Project priority):
| Schedule Manager priority | MS Project priority |
|---|---|
| Highest | 1000 |
| Very high | 800 |
| High | 650 |
| Medium | 500 |
| Medium low | 400 |
| Low | 250 |
| Lowest | 100 |
Task state / percent complete
Microsoft Project does not support Schedule Manager's state types directly; states are derived from Percent Complete:
| MS Project Percent Complete | Schedule Manager state |
|---|---|
| 100 | COMPLETE |
| 0 | NOT STARTED |
| > 0 and < 100 | IN PROGRESS |
Note: The default status of the equivalent state is automatically set.
Other items that do not transfer or behave differently
Calendars cannot be imported or exported.
Split tasks are not supported by Schedule Manager. This option exists in the Microsoft Project plug-in but not in Schedule Manager. Workaround: in Microsoft Project, select Options from the Tools menu and clear the Split in-progress tasks option.
Constraints — Schedule Manager does not support all Microsoft Project constraints, and vice versa:
Microsoft Project Schedule Manager ASAP ASAP ALAP ALAP Must start on Fixed Must finish on Fixed Start no earlier than None Start no later than None Finish no earlier than None Finish no later than None Microsoft Project does not have the option of unlinking a task's Percent Complete from Work Complete. Workaround: before importing or exporting, make sure to check the Is Percent Linked option in Schedule Manager (open the Properties dialog box for a schedule; from the General tab, click Is Percent Linked).
The Microsoft Project plug-in does not support integrated projects (multiple Microsoft Project projects in the same project).
Baselines do not transfer for import/export operations.
When you import from Teamcenter to Microsoft Project, phase gates and proxy tasks are treated as normal tasks without any special attributes — only basic scheduling data is imported. No relationships with other Teamcenter objects are imported, including trace links, deliverables, and workflow information.
Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.plm00054/mpntegration3 · retrieved 2026-07-10