TeamcenterKnowledge

Program Planning > Creating, managing, and assigning deliverables > Add or remove a deliverable within the plan components

Add or remove a deliverable within the plan components

As a program manager or program administrator, you can add program deliverables to, or remove program deliverables from, a program, project, subproject, or event. When you remove a program deliverable, the relationship between the program deliverable and the plan component is removed, but it does not delete the deliverable from Teamcenter.

This procedure provides the process for adding the program deliverable, which is the container for the deliverable instance.

Example: An engine redesign is an example of a program deliverable and the corresponding engine CAD drawing is the deliverable instance associated with that program deliverable.

Add a deliverable to a program, project, subproject, or event

The program deliverable can be created from the Home folder and then added to the program, project, subproject, or event.

Note: If your administrator has configured Teamcenter project security, the deliverable will be assigned to the same Teamcenter Tc_project as the parent program.

When you are adding a deliverable to an event, the due date defaults to the planned date for the event. You can change this to a different date if necessary.

Procedure

  1. Navigate to the program, project, subproject or event in your folder structure or from the program timeline.
  2. Select the desired program, project, subproject, or event.
  3. Click the Deliverables tab.
  4. In the Deliverables section, click Add To.
  5. In the Add panel, do one of the following:
To Do
Search for an existing program deliverable. Click the Search tab. Enter the search criteria and click Search. Select the program deliverable.
Select a program deliverable that was previously copied to the paste buffer using Copy. Click the Palette tab. Select a program deliverable from the Clipboard section.
Select a favorite or recently viewed program deliverable. Click the Palette tab. Select a program deliverable from the Favorites or Recent section.
Add a new program deliverable. Click the New tab. Specify the Type of the program deliverable. Enter the properties for the new program deliverable.
  1. Click Add.

Remove a deliverable from a program, project, subproject, or event

Procedure

  1. Select the deliverable you want to remove.
  2. Click Cut.

Program Planning, 2606 — Unpublished work. © 2025 Siemens