Program Planning > Using the timeline to manage programs > Move the schedule milestone or program event when a dependency is defined
Move the schedule milestone or program event when a dependency is defined
As a program manager, you can move an event to a new date on the program. When an event is moved to a new date, all secondary milestones are automatically moved by the same number of days as the primary event. The event can move backward and forward in time. However, when dependencies are defined between the milestones and events, the following restrictions apply:
- Events cannot be moved to a date on the timeline that occurs prior to secondary objects.
- Events cannot be moved to a date on the timeline that occurs later than the primary objects.
- Only events for which you have write access will be moved.
Note: This action can also be performed on the schedule Gantt.
Procedure
- Open a program that is associated with a schedule.
- Click Schedule Milestones to show the milestones on the Timeline.
- Create a dependency between the milestones and events.
- Click a milestone or event on the Timeline to select it.
- Do one of the following to move the milestone or event to a new date:
| To | Do |
|---|---|
| Move a milestone or event to a new date on the Timeline. | Drag the milestone or event to a new date on the Timeline. |
| Change the date from the Overview tab. | From the Overview tab, click Edit. (Select a layout from Layout Manager to display details below the Timeline, such as the Overview tab.) Under Planned, select a new date. Click Save. |
| Change the date in the Information panel. | Click Information. Click Edit. Under Planned, select a new date. Click Save. |