IPP&E workflow handlers > Action handlers
IPP-incorporate-contingency
Description
This handler incorporates contingency cost in the relevant cost elements of the direct cost on the functional work package revision. If the parent WBS work package and functional work package revision containing the direct cost to modify is released, they are revised and the cost is updated on the revised object.
Syntax
IPP-incorporate-contingency
Arguments
-contingency_type The type of contingency, Risk or Opportunity.
Placement
Requires no specific placement.
Restrictions
None.
Note
A WBS work package is identified based on the Work Package check box on the WBS element revision.