Schedule Management > Creating and managing schedules > Comparing the planned schedule with the current schedule

Create a schedule baseline

Procedure

  1. Open a schedule in Schedule Manager.

  2. Select the schedule and choose Schedule→Baseline Schedule.

    Teamcenter displays the Schedule Baseline dialog box.

  3. Enter a unique name for the baseline in the Baseline Name box.

    Note: If you are copying a baseline from an existing baseline, and you use the same name, the older baseline is overwritten with the new baseline options.

  4. Click Active to make this baseline the active baseline. The active baseline information is shown for the baseline columns when not viewing a specific baseline.

    Note: If this is the first baseline, this option is not available — Teamcenter automatically sets this baseline as active.

  5. Click Copy Baseline to copy information from an existing baseline. In the Copy Settings box, set the following options:

    • Choose Baseline — choose a baseline to copy.
    • Baseline new tasks — baseline all tasks not currently baselined.
  6. In the Task baseline updates section, set one of:

    • Do not update baselines — existing task baselines are not updated.
    • Not started tasks — update the baseline of all tasks that have not started.
    • Update incomplete tasks — update the baseline of all tasks that are not complete.
  7. Click OK.