Modify program deliverable dependencies

You can modify the deliverable dependencies as the program event is worked to completion. When you modify the dependencies, Active Workspace automatically resequences the deliverables based on the modifications you make.

Procedure

  1. Open the desired event from a program's timeline or from its Events tab.
  2. Click the event's Deliverables tab.
  3. Select the deliverable you want to modify.
  4. Click More Commands > Manage > Author Dependencies. The Dependencies panel opens and displays the Preceding, Concurrent, and Succeeding dependencies.
  5. Drag a deliverable to the desired section of the panel. For example, you can drag a deliverable from the Succeeding section to the Concurrent section.
  6. Click Save. A prompt appears asking if you want to resequence the deliverables:
    • Yes — Starts the resequencing process. The amount of time this takes depends on the number of deliverable dependencies modified.
    • No — Does not start the resequencing process; you can resequence later.
    • Run in Background — Runs the resequencing process in the background so you can continue working. Select this option if modifying a large number of deliverable dependencies.
  7. Once resequencing is complete, Active Workspace adjusts the deliverable sequence and updates the Sequence column if necessary.

You can repeat this process with the remaining deliverables to modify the dependencies as needed.