Schedule Management > Creating and managing schedules > Defining tasks, milestones, and work breakdowns > Creating dependencies between tasks
Delete task dependencies (Gantt chart)
Procedure
Position the cursor over the task bar to display a four-headed arrow.
Right-click and choose Dependencies.
Teamcenter displays the Dependencies dialog box.
Select the dependency from either the Predecessor or Successor boxes and click Delete to display the Confirm dialog box.
Click Yes.